Just
a quick update on where we’re at:
·
Brisbane City Council has issued contracts to two timber specialists to
supply the timber decking for the new Pier. The successful companies are
Parkside Group of Companies (from Ayr) and Kennedy's Classic Aged Timbers (from
Narangba).
·
Currently Council has lodged a Development Application for Tidal Works
and a Marine Permit for working in the marine park from the Queensland
Government. Council is awaiting the results of this application.
·
The development application is Impact Assessible – which means the
application will be publically advertised and it will be open for public
submissions (and open to appeal through the Planning and Environment Courts).
·
Tender documents are prepared and ready to be issued once a decision is
made concerning the Development Application and the Marine Permit. Given
the complexity of the work, the tenders are expected to be open for 5 1/2 to 6
weeks.
·
Work will be mostly done in the 2014/15 financial year (with $11.521M
allocated) and completed in the 2015/16 financial year (with the remaining
$7.123M projected for that year).
·
Some of the $11.521M was funding carried over last year (which wasn’t
spent) – you’ll recall $550,000 was carried over from the 2013/14 Budget to the
2014/15 Budget. So the funding allocated is about what was previously proposed.
·
Most of the work will be the removal of the existing Pier, recovery of
materials which can be re-used and to start work building the new Pier, in the
similar style to the current one.
·
The Shorncliffe Pier renewal project is expected to be completed by
early 2016, according to comments by the Lord Mayor in his Budget speech
yesterday